The NBN rollout asbestos crises could cost Telstra $50 million

NBN rollout
Fortunately, there's no asbestos in this pit

Amid growing concerns and news of three more sites in Queensland affected by asbestos during the rollout of the National Broadband Network, Telstra's CEO David Thodey has said that the telco had been managing the risk of asbestos within its network for many years.

As part of the contract with NBN Co, Telstra is responsible for repairs and maintenance of the cabling pits and ducts before NBN Co installs the new fibre-optic lines, a process named "remediation".

Government not impressed by Telstra

Workplace Minister Bill Shorten revealed under opposition pressure letters that were sent to Telstra in 2009 after being contacted by the Australian Workers Union.

The letters expressed his concerns about asbestos in Telstra's aging infrastructure.

According to the letters, Thodey had written back at the time: "(Given) the potential risks of removal, and the prohibitive associated costs, we do not believe that a pro-active pit removal process is justified at this time."

Shorten said that the government had accepted assurances by the telco that the issue was being handled before the NBN rollout began.

"Telstra wrote back and said they had the matter under control. We've seen in recent days and weeks that clearly they haven't," he said.

Via: Herald Sun